Supplier order dates and arrival dates: plan each supplier's orders on its calendar, with a target and a budget
Not every supplier works on a steady cycle. Some take orders only on set dates. Others agree a year of shipments up front, landing in March, June and October, against an annual purchase budget. How you plan orders on a supplier now has two more options for them: Supplier order dates and Arrival dates. Pin the dates, and demand planning works out the rest from the lead time, sizes each order to last until the next arrival, and shows how it compares with your target for each order and with the year's budget.
✨ What this means for you:
- Plan on the supplier's calendar. With Supplier order dates, you pin the dates the supplier takes orders, and each one shows when its stock Arrives. With Arrival dates, you pin when stock should land, and each one shows the date to Order by.
- Each order lasts until the next arrival. The order that's due covers demand until the following arrival lands, plus any safety days, after counting stock already on open purchase orders. A later arrival's stock is never bought early.
- Hit the order value you agreed. Set a Target value per order, and the forecast shows whether the order is on target, over or under. Scale to target adjusts the quantities for you, keeping case packs and minimums.
- Keep the year on budget. Set an Annual purchase budget, and the 12-month plan shows what's committed, what's planned and what's left for each year.
- Ordered dates lock. Raise the purchase order from demand planning, and the date locks to it.
- Amounts in your currency. Demand planning shows money in your account's currency, and a purchase order in another currency is converted before it counts against a target or budget.
Choose how you plan orders
Under the supplier's Settings → Purchasing Defaults, click Edit. How you plan orders has four options:
- Every N weeks: a steady rhythm, as before.
- Supplier order dates: the supplier takes orders on set dates; stock lands a lead time later.
- Arrival dates: pin when stock should land; order-by dates are worked out.
- No cycle: plan with Target Stock Days.
For either kind of date, click Add order date or Add arrival, or add three at once with a spacing such as Every 3 months. Each date can have its own Target value and Notes, and shows its status: Planned, Order day, Order overdue, Missed or Ordered. SKU.io works out the other date of each pair from the supplier's lead time, so set the lead time first. If you switch between order dates and arrival dates, your dates stay, and SKU.io asks you to check them before saving.
Target value per order and Annual purchase budget sit in the same form and work with every option, including Every N weeks and No cycle.
Plan the next order in Demand Planning
When you build a forecast, the supplier's banner says it orders on set dates or plans on arrival dates, and shows the order against its target: within 5% counts as On target, otherwise it reads, for example, 18% under target. Click Scale to target to scale the quantities you can edit to the target, or Reset quantities to put them back. If case packs or minimum order quantities keep the order off target, the banner says by how much. With a budget, a line under it adds up the year so far.
Ordering before the next date only tops stock up until that order arrives. After the last planned date, the supplier is planned with Target Stock Days again. Products with their own lead times, such as those you send by air instead of by sea, keep them.
See the whole year
Click View 12-month plan for every planned order in the next twelve months, with its dates, its status, the date its stock Covers until, its target and its Projected value. Ordered dates show the purchase order total, the next one shows the live suggestion, and later ones are projected from demand. Each year ends with the budget, what's committed on purchase orders, what's planned, and what's left.
When you raise the purchase order from demand planning, the date shows Ordered and links to it. The purchase order's expected arrival date is set to the planned arrival if it doesn't already have one. To unlock the date, delete that purchase order. Schedules set to On each supplier's order cycle run on these order dates too, for just the suppliers due that day.
Money in your account's currency
In Demand Planning, runs, run history, the schedule timeline and order summaries now show amounts in your account's currency instead of a dollar sign, and each purchase order total shows in that order's own currency. Targets, budgets and the supplier's Minimum Purchase Order Value show your currency symbol too.
Where to find it
Set the dates under Contacts → Suppliers → the supplier → Settings → Purchasing Defaults, then build the forecast on Inventory → Demand Planning.
Related guide: Plan purchases on each supplier's order cycle