What is lead time?
Also called Supplier lead time, Replenishment lead time
Lead time is the number of days between placing a purchase order and having the stock received and ready to sell. It adds up the supplier's confirmation, production, transit, customs and receiving time. It sets how early you must reorder: the longer and less reliable it is, the more stock you hold while you wait.
Worked example
You order from an overseas factory. The parts of the wait:
| Stage | Days |
|---|---|
| Supplier confirms the PO | 5 |
| Production | 20 |
| Ocean transit | 25 |
| Customs clearance | 3 |
| Receiving and putaway | 2 |
| Lead time | 55 |
The product sells 12 units a day. Over the wait you sell 12 × 55 = 660 units, so with 150 units of safety stock the reorder point is 660 + 150 = 810 units. Order when available stock drops to 810, not when the shelf looks low.
If you had used the factory’s quoted 30 days, the reorder point would be (12 × 30) + 150 = 510. You would order 300 units too late, and the buffer would run out before the container arrived.
Quoted vs actual
The quoted lead time is what the supplier tells you. The actual lead time is what your receipts show: the date each PO was placed against the date it was received. Track both. A supplier quoting 30 days and delivering in 41 is costing you either stockouts or extra safety stock, and the gap is a fair thing to raise with them.
Count to sellable, not to the dock
Lead time ends when the stock can be sold, not when the truck arrives. If receiving takes three days in a busy month, those three days belong in the number. For stock sent on to Amazon, the time it takes Amazon to check the shipment in is a second leg on top.
What shortens it
Ordering on a fixed cycle so the supplier can plan production, holding components the supplier would otherwise wait for, and shipping by air for the urgent part of an order. Each one costs something, so compare it with the stock you would otherwise carry through the wait.
More terms: Purchasing and planning
- Demand forecasting
- Economic order quantity (EOQ)
- Goods in transit
- HTS code
- Incoterms
- Just-in-time inventory
- Landed cost
- MOQ
- Open-to-buy
- Purchase order (PO)
- Reorder point
- Safety stock
- Sales velocity
- Vendor deposit
Updated · All terms