Use the Inventory Planning report
The Inventory Planning report is your buy plan across every supplier and warehouse in one place. Each row is a product, with its stock, how fast it sells, how long the stock will last, and how many units to order now. Above the table, the reorder summary groups everything that needs ordering by supplier, so you can create purchase orders without building a forecast first. Use it for a quick daily or weekly check. When you want to plan one supplier's order in depth, the report hands you over to Demand Planning.
Before you begin
- Products need a supplier for the report to suggest an order. The lead time comes from the product's supplier listing, the supplier, or your account's default, the same way as in Demand Planning. Set Target Stock Days and Min Stock Level on the supplier product to control how much it suggests. See Set supplier lead times.
- You need access to the Inventory Planning report.
Open the report
- Go to Insights → Reports.
- Click Inventory Planning.
The status line at the top shows how fresh the numbers are. Sales Data and Velocity Cache are recalculated every night at 2 AM; click Refresh next to either one to recalculate now. Under it, the summary shows the number of SKUs, units available, stock value, inbound units, the average days of stock, and the value of dead stock. Click Show Details for more totals.

Find what needs ordering
- Turn on Actionable only to hide products that have no stock, nothing inbound, and no sales. What's left is everything you can act on.
- Click a shortcut chip to jump to a ready-made view:
- Need Reorder shows products with a suggested quantity, with the most revenue at risk first.
- Dead Stock shows products with stock on hand and no sales in 90 days, the most valuable first.
- Narrow the table with the filters: Supplier, Brand, Tag, Warehouse, ABC, XYZ, Risk, Dead Stock, Status, and Lifecycle. Use Lifecycle to leave out discontinued products, or to find the phasing-out ones still worth a final buy. See How product lifecycle works.
- Scroll right to the planning columns. Days of Stock and Stockout Risk show who runs out first, Order By shows the latest date to order, and Reorder Point and Suggested Qty show what to order.

Order by and supplier closures
When you've set up supplier closures, such as Chinese New Year, the report plans around them:
- Order By is the latest date you can order and still have the stock land before the product runs out, with closures taken into account. It reads Order now when even an order placed today lands too late. Hover the date for the reason. A dash means there's nothing to work it out from, for example no sales. Set lead time appears only when no lead time is set anywhere for the product; click it to add one.
- Lead Time, which you add from Columns, shows a chip such as +36 when a closure lengthens the order. Hover the chip for the breakdown, for example 80 d supplier lead time + 22 d Chinese New Year (Jan 30 – Feb 20) + 14 d ramp = 116 d effective.
- Reorder Point, Stockout Risk and Suggested Qty include the extra days.


Inbound cutoffs don't apply in this report, because it doesn't plan for one destination warehouse. See How closures change lead times and order-by dates.
To see how a product's stock runs down over the coming months, click the chart icon beside its SKU (View stock run-down). The product's stock run-down opens in a new tab: its projected stock month by month, with the purchase orders already on the way.

The report has more than 80 columns, but it opens with only a default set. Use Columns to add the others or hide the ones you don't need, then click Save view to keep that layout and filters as a view you can reopen from Views. Hover over the info icon on any column header to see what it measures and how it's calculated. How sales velocity and days of supply work explains the main ones.
Order by supplier
-
Expand Reorder Summary by Supplier. It lists each supplier with products to reorder: the number of Items, the Total Cost, the Landed Cost, the shipment volume in CBM, and how much of a 40-foot Container that volume fills.
-
To order from one supplier, click Create PO on its row. Check the items and total cost, then click Create Draft PO. The purchase order is created as a draft, so you can review it before you send it.

-
To plan that supplier's order in more depth, click Plan in detail. Demand Planning opens with the supplier already selected.

Plan Reorder, in the toolbar, opens Demand Planning for every supplier in the reorder summary at once.
Create orders for selected products
- Select the products in the table.
- Click Create POs in the bar that appears above the table.
- In Create Purchase Orders, choose the Destination Warehouse and whether the orders are Draft or Approved. The products are grouped into one purchase order per supplier.
- Adjust any Order Qty. Turn on Include products without reorder suggestions to add selected products the report doesn't suggest ordering, and enter their quantities yourself.
- Click Create Purchase Orders. A summary lists the purchase orders it created, with links to each one.
Products without a supplier can't go on a purchase order. Assign a supplier to them first.
Whichever way you create them, the order quantities use the same lead time the report shows on each row, which is also the lead time Demand Planning uses: the product's lead time on its supplier, else the supplier's own Lead Time (days), else your account's default, with the measured lead time from your recent purchase orders taking over when it's longer, plus any closure. Before November 2026 the report read only the product's own lead time and ordered on the configured figure, so products that relied on the supplier's or the account's lead time showed Set lead time and no suggestion, and where measured lead times are longer, quantities are now larger.
Compare days of supply on three supply bases
Days of supply depends on which stock you count. The Days of Supply columns show it three ways, each at the average daily sales of the last 30, 60 and 90 days, plus the same figure a year ago.
-
Click Columns and open the Days of Supply group. Only the 30-day columns are shown at first. Tick the 60-day and 90-day ones to add them.
-
Read the columns side by side:
Column Stock it counts Days: Available 30d Available only. Days: + Ready 30d Available plus Ready at Supplier: units on open purchase orders that are finished at the supplier. Days: + All POs 30d Available plus Inbound: everything on open purchase orders. Days: Last Year 30d Stock on hand at the end of the same date last year (today minus 365 days), at the average daily sales of the 30 days that ended that day. Hover over the header to see the exact dates, such as Oct 23, 2025 – Nov 22, 2025. With all warehouses, it adds up the stock and sales of every warehouse. With one warehouse, it counts only that warehouse. Ready at Supplier The units the + Ready columns add. -
Check the cells that don't show a number:
- ∞ means the product had no sales in that window, so the stock never runs out at that pace. In a Last Year column, it shows only when there was stock on hand that day that didn't sell.
- No sales in a Last Year column means there was no stock and no sales on that date last year. Hover over it for the dates it checked.
- — in a + Ready column or Ready at Supplier means no usable Ready at supplier milestone is set. Hover over it to see why, with links to the Inventory Planning setting and Logistics Tracking Fields.
- … in a Last Year column means SKU.io is still calculating last year's figures in the background. The table reloads by itself in a moment. They're recalculated once a day.
- If your history in SKU.io is shorter than a year, a note above the table says when it starts, and the Last Year columns fill in once you have a year of stock and sales history. When your history starts inside the comparison window, the header tooltip says so: those figures count only the sales from then on, so they read high.
-
To find what runs out first on a basis, click its column heading to sort. You can sort every column in the group except the Last Year ones.
How sales velocity and days of supply work explains the calculation.
Choose when stock counts as ready at the supplier
A unit on an open purchase order counts as Ready at Supplier once the order, or its shipment, has an actual date for the milestone you choose. Units that have shipped, or whose shipment is in transit, always count.
- Go to Settings → Inventory → Inventory Planning.
- Pick the Ready at supplier milestone. It's Production complete unless you change it. Clear it to hide the + Ready figures.
- Click Save Changes.
The milestone has to exist and be switched on. If you don't track production yet, go to Settings → Purchasing → Logistics Tracking Fields and click Add production milestones, then record the actual dates on your purchase orders. See Track logistics milestones on purchase orders.
Export or email the report
- Click Export to download the table as it's filtered and sorted now.
- Click Schedule to email it automatically. Name the schedule, choose the Frequency (Daily, Weekly, or Monthly), the Day, Time, and Timezone, the Format (CSV or XLSX), and the Recipients, then click Save Schedule. Every delivery uses the filters, columns, and sort you have on the report when you create the schedule, listed under Scoped to.

Next steps
- Set up supplier closures and inbound cutoffs so order dates plan around factory shutdowns.
- Read the stock run-down grid to see a product's stock month by month.
- Forecast demand and replenish stock to size one supplier's order with a full forecast.
- Replenish stock on a schedule to have forecasts create purchase orders automatically.