# Bill of Materials Software for Brands That Assemble What They Sell

By [Kalvin Mizzi](https://www.sku.io/our-story/) · November 26, 2026

![Cards showing one jar with two sources of demand, using 45 days of cover and 400 jars on hand: 800 jars for gift set builds, 225 sold on its own (5 a day for 45 days), 625 short (1,025 needed minus 400 on hand), and an order of 1,000 at the supplier's minimum. A reorder list reading only the jar's own sales orders none.](https://www.sku.io/_astro/figure.D7XXKBw8_Z2iun6V.webp)

For a brand that assembles what it sells, bill of materials software has one job that a parts list in a spreadsheet can’t do: turn the demand for a finished product into a build quantity, and the builds into a component order placed early enough. In the made-up example on this page, a gift set and loose sales need 1,025 jars over 45 days, the shelf holds 400, a reorder list orders none, and the set ends up out of stock for at least 13 days of its best season.

“Bill of materials software” often means a tool for engineers managing drawings and revisions, or a system for a factory. This page is for a different reader: you sell kits, gift sets or filled products on Shopify, Amazon and wholesale, you put them together yourself or at a co-packer, and your components come from suppliers with lead times.

![A made-up example: 800 gift set builds and 225 loose sales need 1,025 jars against 400 on hand, so 625 are short and the minimum makes the order 1,000](https://www.sku.io/_astro/figure.D7XXKBw8_1xIgG6.webp)

## The problem a recipe alone doesn’t solve

Someone who runs operations at a consumer brand that sells direct and wholesale described it to me: “Some of our products can be made up of bundles or components and it’s really difficult to understand, you know, how much should we sell on this when it would be made up of xyz?”

A recipe tells you what’s in one unit. It doesn’t tell you how many units to build, or what that does to a component three products share. And the sales reports make it worse, because they show the gift set selling and its components barely moving. A component’s real demand is inside the sets.

## What it looked like on our own shelf

Besides SKU.io, I run a company that sells car parts online. One of the parts is a fuel pump. We sell it on its own, and we also box it with an installation kit and sell that as two different kits.

Over the twelve months to October 2025 the pump sold 251 on its own. Our builds used 791. Three quarters of the pump’s demand never showed up in the pump’s sales.

At the end of February 2025 there were 251 pumps on the shelf. In the three months before that we had sold 4 on their own. Read by its own sales, that was years of stock. Then came the builds: 120 in March, 60 in April, 120 in May. At the end of May there were 3 pumps left.

A shipment of 1,000 landed on June 6. June’s builds came to 31. July’s were 180.

A list that read the pump’s own sales would have shown it fully stocked the whole way down. The made-up example below has the same shape with rounder numbers, so the arithmetic is easier to follow.

## An example: a gift set before Mother’s Day

*This is a made-up example. The brand and its numbers are invented to show the arithmetic and what goes wrong.*

Picture a bath brand, Saltmarsh, 45 days before Mother’s Day. Its gift set is one jar of bath salts, two soaps and a printed box. The jar also sells on its own.

The set is expected to sell 20 a day over the next 45 days, so 900 sets. There are 100 on the shelf, which leaves 800 to build.

| Component | Per set | For 800 builds | Sold on its own, 45 days | Total need | On hand | Short |
| --- | --- | --- | --- | --- | --- | --- |
| Bath salts jar | 1   | 800 | 225 (5 a day) | 1,025 | 400 | 625 |
| Soap | 2   | 1,600 | none | 1,600 | 1,900 | 0   |
| Printed box | 1   | 800 | none | 800 | 450 | 350 |

The box is easy: the supplier ships in cases of 50 and delivers in two weeks, so 350 is 7 cases. The jar supplier has a minimum of 1,000, so 625 short becomes an order of 1,000 at $1.80 each. That’s $1,800, with 375 jars left over. At 5 a day those are 75 days of loose sales, which is a reasonable price for keeping the set in stock.

Here is how it goes wrong. The reorder list looks at the jar’s own sales: 225 needed over 45 days, 400 on the shelf, nothing to order. Nobody orders jars. The first 400 builds go ahead, and the shortage shows up when the jars run out.

## The date matters more than the quantity

The 100 sets on the shelf, plus the 400 that the jars on hand can build, last 25 days at 20 a day. Jars take 35 days to arrive and the build takes 3, so a jar order placed today produces more sets on day 38. Even ordering today, the set is out of stock from day 25 to day 38: 13 days, 260 sets, and at $14 of profit a set, $3,640.

Wait until the jars run out to order, and new sets arrive on day 63, after Mother’s Day. The last 20 days of the season sell nothing: 400 sets and $5,600. (Jars sold loose in the meantime make both figures a little worse.)

The quantity was never the hard part. The last day to order jars was the set’s run-out date, minus the build time, minus the jar’s lead time, and that day was 13 days ago. A parts list has no dates in it at all. In SKU.io every row of the plan carries an **Order by** date and is marked Late, Order now or Order soon, so the jar line would have shown up as due while there was still time.

## What to look for

**A recipe per product, with versions.** In SKU.io a bill of materials is a recipe with a quantity per finished unit for each component and an expected scrap percentage where some material is always lost. It’s versioned, and it has to be active before anything is planned or built against it. A product whose recipe is still a draft shows up in the plan as something it can’t supply, with that reason, instead of silently dropping out.

**A plan that reads the recipes.** SKU.io’s Make, buy & move plan gives each product a row that says make, buy or transfer. The buy rows include the components the planned builds will use, and a build row opens to show each component: needed per unit and in total, on hand, short, and who supplies it.

**Re-sizing when you change a build.** Cut the build from 800 to 600 and the jar need should drop by 200 without anyone redoing the sum. Raise it and the components that now run short should be added.

**A build you can record in one step.** For light assembly you don’t want a factory workflow. SKU.io has a one-screen build: pick the product, the quantity and the warehouse, and the components come off the shelf as the finished stock goes on, costed from what was consumed. It runs in reverse too, to break sets back into parts after a season.

**Kits and bundles kept apart.** A kit is assembled ahead of time and stocked as its own product. A bundle is sold as a set and picked from its parts when the order comes in, so it never has stock of its own. They need different handling, and [where a bundle becomes its parts](https://www.sku.io/where-a-bundle-becomes-its-parts/) is about what happens when nobody decides which is which.

**Someone else doing the build.** If a co-packer assembles for you, the components should be planned at their site and the purchase orders should deliver there.

**Drafts.** The plan should create draft manufacturing orders and draft purchase orders that a person approves. In SKU.io a schedule can create purchase orders on its own. Builds wait for you.

## What this page isn’t about

It isn’t about engineering bills of materials. If you need drawings, part revisions and change approvals tied to CAD files, that’s product lifecycle software, and tools like OpenBOM and Arena are built for it.

It also isn’t a full account of manufacturing in SKU.io. Beyond planning there are manufacturing orders with operations and labor time, a production schedule, contract manufacturing, and a separate MRP module for time-phased planning. If running a production floor is your main problem, test those against software built for factories, on your own data. I’d rather you find the edge in a trial than in month three.

And if you assemble a few dozen sets a month from parts you can see from your desk, a spreadsheet is fine. There’s a free [bill of materials template](https://www.sku.io/templates/bill-of-materials-template/) that costs a recipe and works out what a build needs.

## Where to start

Pick the component that the most finished products share, and do the jar sum above for it by hand once. If the answer surprises you, the planning is worth automating. The guide to [creating a recipe](https://www.sku.io/docs/guides/manufacturing/recipes/create-a-recipe-bom/) shows the set-up in SKU.io, and the [demand planning software guide](https://www.sku.io/demand-planning-software/#make-and-move) shows where builds sit beside purchases and transfers in one plan. If you sell on more than one channel and build some of what you sell, [book a call](https://www.sku.io/book/) and bring that component.

![Kalvin Mizzi, founder of SKU.io](https://www.sku.io/_astro/the-story-of-sku.BNjQHdxV_Z4P6NF.webp)

Written by

[Kalvin Mizzi](https://www.sku.io/our-story/) Founder, SKU.io

Kalvin has run his own multi-channel e-commerce business since 2008 and built the system behind it, which became SKU.io. He still gives every demo personally.

-   [LinkedIn](https://www.linkedin.com/in/kalvinmizzi/)
-   [X](https://x.com/kalvinmizzi)

## Keep reading

-   [Order in Your Supplier's Unit, Stock in Yours: Cases, Bags and Purchase Units of Measure](https://www.sku.io/order-in-your-suppliers-unit/)Nov 27, 2026
-   [What to Put on a Purchase Order for a Factory: Pictures, Specs and Packing](https://www.sku.io/purchase-order-for-a-factory/)Nov 27, 2026
-   [Request for Quote: Get Prices From Several Suppliers and Compare Them Line by Line](https://www.sku.io/request-quotes-from-several-suppliers/)Nov 27, 2026